Question: A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $25,000. The
A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $25,000. The impact on the project brought about by these risks is estimated at $65,000. What value should be entered into the management reserve for these risks?