Question: A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $50,000. The
A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $50,000. The impact on the project brought about by these risks is estimated at $125,000. What value should be entered into the management reserve for these risks?
$ 125,000
$ 175,000
$ 50,000
$ 0