Question: Ankit Aggarwal PM Can A project manager and the project team identify several specific risks in a project. The expected value of these risks
Ankit Aggarwal PM Can A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $8,000. The impact on the project brought about by these risks is estimated at $40,000. What value should be entered into the management reserve for these risks? $40,000 $48,000 $0 $8,000 5:56 p.m.