Question: A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $10,000. The

A project manager and the project team identify several specific risks in a project. The expected value of these risks is estimated at $10,000. The impact on the project brought about by these risks is estimated at

$40,000. What value should be entered into the contingency reserve for these risks?

a. $10,000

b. $40,000

c. $0

d. $25,000