Question: A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?

A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?

Question 5 options:

The activity can be delayed by one week without delaying the project duration.

If the activity is delayed by one week, the project is delayed by one week.

The activity is a critical activity.

The activity becomes non-critical if it is delayed by one week.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!