Question: A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?
A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?
Question 5 options:
|
|
The activity can be delayed by one week without delaying the project duration.
|
|
|
If the activity is delayed by one week, the project is delayed by one week.
|
|
|
The activity is a critical activity.
|
|
|
The activity becomes non-critical if it is delayed by one week.
|