Question: A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?
A project manager finds that a particular activity has a slack of one week based on the critical path method (CPM). Which statement is correct?
| The activity can be delayed by one week without delaying the project duration. | ||
| "If the activity is delayed by one week, the project is delayed by one week." | ||
| The activity is a critical activity. | ||
| The activity becomes non-critical if it is delayed by one week. |