Question: A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and

A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the following methods is the project manager MOST likely using to develop the schedule?

A.Critical chain

A.

Critical chain

B.Baseline

B.

Baseline

C.Precedence diagram

C.

Precedence diagram

D.Arrow diagram

D.

Arrow diagram

E.Sprint plan

E.

Sprint plan

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!