Question: A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and
A project manager has developed a schedule in which all tasks start as late as possible, and there is a focus on buffer utilization and work being completed in shorter periods of time. Which of the following methods is the project manager MOST likely using to develop the schedule?
A.Critical chain
A.
Critical chain
B.Baseline
B.
Baseline
C.Precedence diagram
C.
Precedence diagram
D.Arrow diagram
D.
Arrow diagram
E.Sprint plan
E.
Sprint plan