Question: A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly
A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the organization would be the best choice. #rationale In many cases, the project team approach is the optimum approach for completing a project when you view it solely from the standpoint of what is best for completing the project.
A functional
B balanced matrix
C weak matrix
D strong matrix
E projectized