Question: A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly
A project manager is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the organization would be the best choice.
Question options: functional
balanced matrix
weak matrix
strong matrix
projectized