Question: A project manager is currently documenting rules for schedule performance measurement through earned value management - schedule variance (SV) and schedule performance index (SPI). Which
A project manager is currently documenting rules for schedule performance measurement through earned value management - schedule variance (SV) and schedule performance index (SPI). Which process is the project manager working in? A. Develop schedule B. Project schedule management C. Plan procurement management D. Plan schedule management