Question: A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following

A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to review the status of the project. Based on the information provided, what is the Estimate at Completion (EAC) of the project?
Task Name Start Date End Date Duration (Days) Planned Value Actual Cost Percent Complete
Define 01-Aug 31-Aug 30 $ 12 $ 17100%
Measure 01-Sep 30-Sep 29 $ 52 $ 27100%
Analyze 01-Oct 31-Oct 30 $ 56 $ 4675%
Improve 01-Nov 30-Nov 29 $ 90.00-0%
Control 01-Dec 31-Dec 30 $ 20.00-0%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!