Question: A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following
A project manager is currently managing a manufacturing process improvement project which will be completed in five phases. The project manager has prepared the following chart to review the status of the project as at October 31st.
| Task Name | Start Date | End Date | Planned Value | Actual Cost | Percent Completed |
| Analysis | 01-Aug | 31-Aug | 100 | 120 | 100% |
| Design | 01-Sep | 30-Sep | 400 | 280 | 50% |
| Build | 01-Oct | 31-Oct | 550 | 320 | 75% |
| Test | 01-Nov | 30-Nov | 900 | 0 | 0% |
| Deploy | 01-Dec | 31-Dec | 200 | 0 | 0% |
i) What is the plan value at the stated status date? Give your answer to two (2) decimal places e.g. 11.54
What is the earned value at the stated status date? Give your answer to two (2) decimal places e.g. 11.54
What is the Actual Cost at the stated status date? Give your answer to two (2) decimal places e.g. 11.54
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts