Question: A project manager oversees a fundraising project that involves selling coupon books. Which of the following is a change to the project that needs to

A project manager oversees a fundraising project that involves selling coupon books.
Which of the following is a change to theproject thatneeds to be managed?
A.)
One of the businesses listed in the book is not honoring the specified discount.
B.)
One team member cannot help with the distribution, and another team member arranges to go in his place.
C.)
Some people purchase the coupon book just to make a donation and do not actually use them.
D.)
The CEO offers to donate astore gift card to use for the prize.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock