Question: A project network is shown below. Activity Precedence Activities Optimistic Most Probable Pessimistic Time (weeks) A -- 1 5 10 B -- 2 4 8
A project network is shown below.
|
Activity | Precedence Activities | Optimistic Most Probable Pessimistic Time (weeks) |
| A | -- | 1 5 10 |
| B | -- | 2 4 8 |
| C | -- | 4 8 12 |
| D | A, B | 2 4 8 |
| E | C | 10 12 14 |
| F | C | 4 10 16 |
| G | D, E | 1 3 5 |
| H | E | 1 2 3 |
| I | E, F | 2 5 7 |
- What is the ES, EF, LS, and LF for activity G?
| A. | ES = 20, EF = 23, LS = 21, and LF = 24 | |
| B. | ES = 20, EF = 23, LS = 21.83, and LF = 24.83 | |
| C. | ES = 20, EF = 23, LS = 22, and LF = 25 | |
| D. | ES = 19, EF = 23, LS = 21, and LF = 24. |