Question: A project network is shown below. Activity Precedence Activities Optimistic Most Probable Pessimistic Time (weeks) A -- 1 5 10 B -- 2 4 8

A project network is shown below.

Activity

Precedence Activities

Optimistic Most Probable Pessimistic Time (weeks)

A

--

1 5 10

B

--

2 4 8

C

--

4 8 12

D

A, B

2 4 8

E

C

10 12 14

F

C

4 10 16

G

D, E

1 3 5

H

E

1 2 3

I

E, F

2 5 7

  • What is the ES, EF, LS, and LF for activity G?
A.

ES = 20, EF = 23, LS = 21, and LF = 24

B.

ES = 20, EF = 23, LS = 21.83, and LF = 24.83

C.

ES = 20, EF = 23, LS = 22, and LF = 25

D.

ES = 19, EF = 23, LS = 21, and LF = 24.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!