Question: A project network is shown in the figure. A project network with 12 activities and 14 directed arcs is shown. Activity Start is connected to
A project network is shown in the figure.
A project network with 12 activities and 14 directed arcs is shown.
- Activity Start is connected to activity A.
- Activity A is connected to activity B, to activity C, and to activity D.
- Activity B is connected to activity E and to activity F.
- Activity C is connected to activity G.
- Activity D is connected to activity H.
- Activity E is connected to activity I.
- Activity F is connected to activity J.
- Activity G is connected to activity J.
- Activity H is connected to activity J.
- Activity I is connected to activity Finish.
- Activity J is connected to activity Finish.
- Activity Finish has no arcs directed to other activities.
Activities A-J have numeric values displayed under the Activity label. These values are given below:
- A: 3
- B: 4
- C: 3
- D: 7
- E: 7
- F: 6
- G: 9
- H: 6
- I: 5
- J: 7
Use the network of related activities with their duration times (weeks) to complete a row for each activity under the column headings below. (For the precedence activities, enter your answers as comma-separated lists. If an activity does not have immediate predecessors, enter NONE.)
ActivityPrecedence ActivitiesActivity Time (weeks)ESLSEFLFSlackCritical Path?A ---Select--- Yes NoB ---Select--- Yes NoC ---Select--- Yes NoD ---Select--- Yes NoE ---Select--- Yes NoF ---Select--- Yes NoG ---Select--- Yes NoH ---Select--- Yes NoI ---Select--- Yes NoJ ---Select--- Yes NoStep by Step Solution