Question: A project network is shown in the figure. A project network with 10 activities and 13 directed arcs is shown. Activity Start is connected to
A project network is shown in the figure.
A project network with 10 activities and 13 directed arcs is shown.
- Activity Start is connected to activity A.
- Activity A is connected to activity B and to activity C.
- Activity B is connected to activity D and to activity E.
- Activity C is connected to activity F and to activity H.
- Activity D is connected to activity F and to activity H.
- Activity E is connected to activity G.
- Activity F is connected to activity G.
- Activity G is connected to activity Finish.
- Activity H is connected to activity Finish.
- Activity Finish has no arcs directed to other activities.
For the project represented above, determine the earliest and latest start and finish times for each activity.
| Activity | Duration | ES | LS | EF | LF | Slack |
|---|---|---|---|---|---|---|
| A | 7 | |||||
| B | 5 | |||||
| C | 7 | |||||
| D | 3 | |||||
| E | 7 | |||||
| F | 3 | |||||
| G | 7 | |||||
| H | 9 |
Determine the expected overall completion time.