Question: A project network is shown in the figure. A project network with 11 activities and 16 directed arcs is shown. Activity Start is connected to

A project network is shown in the figure.

A project network with 11 activities and 16 directed arcs is shown.

Activity Start is connected to activity A, to activity B, and to activity C.

Activity A is connected to activity D and to activity G.

Activity B is connected to activity D.

Activity C is connected to activity E and to activity F.

Activity D is connected to activity G.

Activity E is connected to activity G, to activity H, and to activity I.

Activity F is connected to activity I.

Activity G is connected to activity Finish.

Activity H is connected to activity Finish.

Activity I is connected to activity Finish.

Activity Finish has no arcs directed to other activities.

Activities A-I have numeric values displayed under the Activity label. These values are given below:

A: 9

B: 8

C: 12

D: 4

E: 12

F: 10

G: 6

H: 5

I: 8

Activity Precedence Activities Activity Time (weeks) ES LS EF LF Slack Critical Path?
A ---Select--- Yes No
B ---Select--- Yes No
C ---Select--- Yes No
D ---Select--- Yes No
E ---Select--- Yes No
F ---Select--- Yes No
G ---Select--- Yes No
H ---Select--- Yes No
I ---Select--- Yes No

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!