Question: A project network is shown in the figure. A project network with 11 activities and 16 directed arcs is shown. Activity Start is connected to
A project network is shown in the figure.
A project network with 11 activities and 16 directed arcs is shown.
Activity Start is connected to activity A, to activity B, and to activity C.
Activity A is connected to activity D and to activity G.
Activity B is connected to activity D.
Activity C is connected to activity E and to activity F.
Activity D is connected to activity G.
Activity E is connected to activity G, to activity H, and to activity I.
Activity F is connected to activity I.
Activity G is connected to activity Finish.
Activity H is connected to activity Finish.
Activity I is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Activities A-I have numeric values displayed under the Activity label. These values are given below:
A: 9
B: 8
C: 12
D: 4
E: 12
F: 10
G: 6
H: 5
I: 8
| Activity | Precedence Activities | Activity Time (weeks) | ES | LS | EF | LF | Slack | Critical Path? |
|---|---|---|---|---|---|---|---|---|
| A | ---Select--- Yes No | |||||||
| B | ---Select--- Yes No | |||||||
| C | ---Select--- Yes No | |||||||
| D | ---Select--- Yes No | |||||||
| E | ---Select--- Yes No | |||||||
| F | ---Select--- Yes No | |||||||
| G | ---Select--- Yes No | |||||||
| H | ---Select--- Yes No | |||||||
| I | ---Select--- Yes No |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts