Question: A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following activities: Activity Immediate Predecessor ( s

A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following activities:
Activity Immediate
Predecessor(s) Durations (weeks)
to tm tp
Start -
A Start 112029
B A 258
C A 183042
D B 71013
E Start 314043
End C, D, E
What is the estimated slack time for Activity E?
Question 14Answer
a.
11 weeks
b.
12 weeks
c.
9 weeks
d.
3 weeks
e.
0 weeks