Question: A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the followin activities DURATIONS (weeks) ACTIVITY Start A

A project superintendent is about to begin work
A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the followin activities DURATIONS (weeks) ACTIVITY Start A B D E PRECEDES A, E B, C D End End End to 11 2 18 7 31 20 5 30 10 40 te 29 8 42 13 43 What is the estimated expected (mean) duration for Activity E? Select one: O a. 31 weeks O b. 38 weeks Oc43 weeks O d. 39 weeks O e 40 weeks