Question: A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following five activities: DURATIONS (weeks) 11 29

A project superintendent is about to begin work
A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following five activities: DURATIONS (weeks) 11 29 ACTIVITY Start A B D E PRECEDES . B, C D End End End 18 7 31 20 5 30 10 40 42 13 43 What is the estimated slack time for Activity E? Select one: a. 9 weeks b. 12 weeks c. 3 weeks O d. 11 weeks e. O weeks