Question: A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following five activities: What is the estimated
A project superintendent is about to begin work on a freeway resurfacing project, which is comprised of the following five activities: What is the estimated expected (mean) duration for project completion?
Select one:
a.
35 weeks
b.
50 weeks
c.
104 weeks
d.
105 weeks
e.
39 weeks