Question: A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (

A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic), it will take 15 days, and if conditions are ideal (optimistic), it will take only 3 days. Using the PERT three-point estimation method, what is the expected time for this work package?
Group of answer choices
18 days
14 days
9 days
26.67 days
None of the aboveA project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic), it will take 15 days, and if conditions are ideal (optimistic), it will take only 3 days. Using the PERT three-point estimation method, what is the expected time for this work package?
Group of answer choices
18 days
14 days
9 days
26.67 days
None of the above

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!