Question: A project team estimates that a work package is most likely to have a duration of 1 6 days. However, under the worst possible conditions

A project team estimates that a work package is most likely to have a duration of 16 days. However, under the worst possible conditions (pessimistic), it will take 40 days, and if conditions are ideal (optimistic), it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?