Question: A project team estimates that a work package is most likely to have a duration of 1 6 days. However, under the worst possible conditions
A project team estimates that a work package is most likely to have a duration of days. However, under the worst possible conditions pessimistic it will take days, and if conditions are ideal optimistic it will take only days. Using the PERT threepoint estimation method, what is the expected time for this work package?