Question: A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic)
A project team estimates that a work package is most likely to have a duration of 9 days. However, under the worst possible conditions (pessimistic) it will take 15 days, and if conditions are ideal (optimistic), it will take only 3 days. Using the PERT three-point estimation method, what is the expected time for this work package?
18 days
14 days
9 days
26.67 days
None of the above