Question: A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions (pessimistic)
A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions (pessimistic) it will take 40 days, and if conditions are ideal (optimistic), it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
