Question: A project team has established a network diagram for a project, however did not include all the information required. The project manager has some information

A project team has established a network diagram for a project, however did not include all the information required.
The project manager has some information available about the project activities. Below is the list of all the clues he knows:Each of the activities, labeled \(\mathrm{A}-\mathrm{G}\), has a different duration between 1 and 7 weeks. Durations (weeks) are 1,2,3,4,5,6,7.One activity has a float of 3 weeks. Another activity has a float of 6 weeks. Two activities have a float of 8 weeks.There exists only one critical path, and its duration is the largest possible number given the above duration of the activities.Activity E has the smallest amount of float that is non-zero.The EF of Activity A is 4 Weeks, which is different than the LF of A.Activity F takes at least 2 Weeks longer than Activity C.
Using your knowledge about CPM and applying the Forward Pass and Backward Pass rules, identify all entries in the table below:
 A project team has established a network diagram for a project,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!