Question: A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point
A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances.