Question: A project to extend an existing manufacturing facility is being undertaken using the NEC 4 Engineering and Construction Contract main option C and X 5
A project to extend an existing manufacturing facility is being undertaken using the NEC Engineering and Construction Contract main option C and X and X The period between Completion of the whole of the works and the defects date is weeks. The works include the construction of a new warehouse which will link to the existing production building. Section of the warehouse is a reinforced concrete slab with a completion date of October. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor is to submit a first programme for acceptance is four weeks. The period for reply is three weeks.
QUESTION
If the works had been procured using a priced contract with Activity Schedule what information, additional to that required by the core clauses, would the Contractor be required to provide when submitting a programme for acceptance?
Select ONE option
Information which shows how each activity on the Activity Schedule relates to the operations on the programme.
The Contractor's planned method of working for each operation.
The additional Price for Work Done to Date associated with each time risk allowance.
Other information which the Scope requires.
A forecast of the Price for Work Done to Date for each operation shown on the programme.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock