Question: A project to extend an existing manufacturing facility is being undertaken using the NEC 4 Engineering and Construction Contract main option C and X 5
A project to extend an existing manufacturing facility is being undertaken using the NEC Engineering and Construction Contract main option C and X and X The period between Completion of the whole of the works and the defects date is weeks. The works include the construction of a new warehouse which will link to the existing production building. Section of the warehouse is a reinforced concrete slab with a completion date of October. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor is to submit a first programme for acceptance is four weeks. The period for reply is three weeks.
QUESTION
Later on in the contract, the Contractor does submit its first programme to the Project Manager for acceptance. The Project Manager identifies a problem with the order of the operations for the work linking the production building to the new warehouse. Also, drawings given in the Scope show that underground drainage is required but this work is not identified in the programme.
Which of the following best describes the reasons why the Project Manager could decide not to accept the programme?
Select ONE option
Clause bullet points and
Clause bullet points and
Clause and
Clause and clause bullet point
Clause bullet points and
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
