Question: A project to extend an existing manufacturing facility is being undertaken using the NEC 4 Engineering and Construction Contract main option C and X 5
A project to extend an existing manufacturing facility is being undertaken using the NEC Engineering and Construction Contract main option C and X and X The period between Completion of the whole of the works and the defects date is weeks. The works include the construction of a new warehouse which will link to the existing production building. Section of the warehouse is a reinforced concrete slab with a completion date of October. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor is to submit a first programme for acceptance is four weeks. The period for reply is three weeks.
QUESTION
If the Project Manager gives the Contractor an instruction to stop work, what other communications does the contract require the Project Manager to give? Select the TWO most appropriate options.
Select TWO options
Make a proposal to the Contractor for acceleration.
Certify Completion of the work completed before the instruction to stop work was given.
If and when appropriate, instruct the Contractor to recommence the work.
Notify the Supervisor.
Notify the Contractor of a compensation event.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock