Question: A project to extend an existing manufacturing facility is being undertaken using the NEC 4 Engineering and Construction Contract main option C and X 5

A project to extend an existing manufacturing facility is being undertaken using the NEC4 Engineering and Construction Contract main option C and X5 and X7. The period between Completion of the whole of the works and the defects date is 52 weeks. The works include the construction of a new warehouse which will link to the existing production building. Section (1) of the warehouse is a reinforced concrete slab with a completion date of 30 October. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor is to submit a first programme for acceptance is four weeks. The period for reply is three weeks.
QUESTION 6
If the Project Manager gives the Contractor an instruction to stop work, what other communications does the contract require the Project Manager to give? Select the TWO most appropriate options.
Select TWO options
Make a proposal to the Contractor for acceleration.
Certify Completion of the work completed before the instruction to stop work was given.
If and when appropriate, instruct the Contractor to re-commence the work.
Notify the Supervisor.
Notify the Contractor of a compensation event.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!