Question: A project to extend an existing manufacturing facility is being undertaken using the NEC 4 Engineering and Construction Contract main option C and X 5
A project to extend an existing manufacturing facility is being undertaken using the NEC Engineering and Construction Contract main option C and X and X The period between Completion of the whole of the works and the defects date is weeks. The works include the construction of a new warehouse which will link to the existing production building. Section of the warehouse is a reinforced concrete slab with a completion date of October. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor is to submit a first programme for acceptance is four weeks. The period for reply is three weeks.
QUESTION
The Project Manager certifies Completion of the reinforced concrete slab on November. When is the defects date for the reinforced concrete slab?
Select ONE option
weeks after the Project Manager certified Completion of the slab.
weeks after the Client takes over of the whole of the works.
The defects date is the Defects Date unless later changed in accordance with the contract.
weeks after the date on which Completion of the whole of the works is certified.
weeks after the Completion Date for the whole of the works.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock