Question: A project whose critical path has an estimated time of 1 2 0 days with a variance of 1 0 0 has a 2 0

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before which day (rounded to nearest day)?
Select one:
a.120
b.124
c.220
d.112
e.98