Question: A project whose critical path has an estimated time of 1 2 0 days with a variance of 1 0 0 has a 2 0

A project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!