Question: Samuel conducts a project. His project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance

Samuel conducts a project. His project whose
Samuel conducts a project. His project whose critical path has an estimated time of 120 days with a variance of 100 has a 20% chance that the project will be completed before day rounded to new day) O 98 O 112 O 120 O 124 O 220