Question: A project with a Schedule Variance ( S V ) > 0 is a project that is: A . On schedule B . Ahead of

A project with a Schedule Variance (SV)>0 is a project that is:
A. On schedule
B. Ahead of schedule
C. Behind schedule
D. Over budget
Activity crashing involves reducing the duration of all project activities to reduce the project duration:
A. True
B. False
The two types of negotiation are:
A. Binding and non-binding
B. Friendly and aggressive
C. Fair and Unfair
D. Interest and position
E. Non-biased and biased
A win-win resolution is typically associated with which of the following techniques:
A. Dispute Review Board
B. Arbitration
C. Litigation
D. None of the above
The contractor can/start project mobilization when they receive a Notice to Proceed from Owner:
A. True
B. False
In a LSM schedule, assume activity A has a rate of progress of 200 LF/day and activity B has a rate of progress of 100LF? day. The total project length is 1,200LF. The contractor decides to have a 400 LF buffer between the start of the two activities A and B. What is the start and end times for activity B assuming activity A starts at Zero?
A.2,7
B.1,12
C.2,14
D.2,12
An interest based negotiation leads parties in a dispute to achieve:
A. Non zero sum solution
B. Sum sum solution
C. Zero sum solution
D. Non sum sum solution
 A project with a Schedule Variance (SV)>0 is a project that

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!