Question: A project with a Schedule Variance ( S V ) > 0 is a project that is: A . On schedule B . Ahead of
A project with a Schedule Variance is a project that is:
A On schedule
B Ahead of schedule
C Behind schedule
D Over budget
Activity crashing involves reducing the duration of all project activities to reduce the project duration:
A True
B False
The two types of negotiation are:
A Binding and nonbinding
B Friendly and aggressive
C Fair and Unfair
D Interest and position
E Nonbiased and biased
A winwin resolution is typically associated with which of the following techniques:
A Dispute Review Board
B Arbitration
C Litigation
D None of the above
The contractor canstart project mobilization when they receive a Notice to Proceed from Owner:
A True
B False
In a LSM schedule, assume activity A has a rate of progress of LFday and activity has a rate of progress of day. The total project length is The contractor decides to have a LF buffer between the start of the two activities A and B What is the start and end times for activity B assuming activity A starts at Zero?
A
B
C
D
An interest based negotiation leads parties in a dispute to achieve:
A Non zero sum solution
B Sum sum solution
C Zero sum solution
D Non sum sum solution
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock