Question: A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80 indicates which of the following? Question 3 options: Project is
A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80 indicates which of the following? Question 3 options: Project is ahead of schedule and under budget Projec