Question: A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80 indicates which of the following? Select one: a. Project is
A project with both Schedule Performance Index (SPI) and Cost Performance Index (CPI) of 0.80 indicates which of the following?
Select one:
a. Project is 20% ahead of schedule
b. Project is behind schedule and over budget
c. Project is behind Schedule and under budget
d. Project is ahead of schedule and over budget
e. Project is ahead of schedule and under budget