Question: Jan Feb Mar Apr Activity Planned Costs % Completed Value Clearing 2 2 1 0 0 Leveling 1 4 1 0 0 Drainage 2 3

Jan Feb Mar Apr
Activity
Planned
Costs
%
Completed
Value
Clearing 22100
Leveling 14100
Drainage 2380
Paving 1550
Construction 1250
Monthly
Planned Costs
Cumulative
Planned Costs
Actual Costs 39520
Cumulative
Actual Costs
Calculate:
a) The Total Planned Value (PV)
b) The Total Earned Value (EV)
c) The Total Actual Cost of Work Performed