Question: A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution. Activity
A project's critical path is ABDE. The project activity information (in weeks) are as follows. Assume the project finish time follows a normal distribution.
| Activity | A | B | C | D | E | F |
| Expected FT | 5 | 8 | 5 | 7 | 3 | 4 |
| Variance | 3 | 4 | 2 | 7 | 9 | 2 |
If the project deadline is set to be 20 weeks, then what is the z-value to determine the probability that the project will be finished before the given deadline?