Question: A project's duration can be reduced by: Select one: a . Adding shorter routes around the critical path. b . Shortening the duration of critical

A project's duration can be reduced by:
Select one:
a.
Adding shorter routes around the critical path.
b.
Shortening the duration of critical path tasks.
c.
Completing the backward pass first.
d.
Adding tasks to the critical pat