Question: A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 5

A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 52 days. They have developed estimated time durations in days for the project as shown in the following table.
\table[[Activity,Immediate Predecessor Activities,Optimistic Time (t_(0)),Most Likely Time (t_(m)),Pessimistic Time (t_(p))],[A,,8,10,13],[B,A,4,8,12],[C,A,8,13,18],[D,A,7,7,16],[E,B,3,4,6],[F,C,E,8,10,11],[G,B,10,12,14],[H,B,D,16,19,22],[I,B,D,8,13,18],[J,F,G,H,6,8,12]]
Determine the estimated duration of the project.
38 days
46 days
52 days
67 days
 A Research and Development team is creating a project plan for

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!