Question: A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 5
A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in days. They have developed estimated time durations in days for the project as shown in the following table.
tableActivityImmediate Predecessor Activities,Optimistic Time tMost Likely Time tmPessimistic Time tpABACADAEBFCEGBHBDIBDJFGH
Determine the estimated duration of the project.
days
days
days
days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
