Question: A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 6

A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 60 days. They have developed the following estimated time durations in days for the project. Determine the critical path of the project.
Activity
Immediate Predecessor
Activities
Optimistic
Time (to)
Most Likely Time (tm)
Pessimistic
Time (tp)
A
10
12
15
B
A
6
10
14
C
A
10
15
20
D
A
9
9
18
E
B
5
6
8
F
C, E
10
12
13
G
B
12
14
16
H
B, D
18
21
24
I
B, D
10
15
20
J
F, G, H
8
10
14
Group of answer choices
A-C-F-J
A-B-I
A-B-G-J
A-D-H-J

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!