Question: A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 6
A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in days. They have developed the following estimated time durations in days for the project. Determine the critical path of the project.
Activity
Immediate Predecessor
Activities
Optimistic
Time to
Most Likely Time tm
Pessimistic
Time tp
A
B
A
C
A
D
A
E
B
F
C E
G
B
H
B D
I
B D
J
F G H
Group of answer choices
ACFJ
ABI
ABGJ
ADHJ