Question: A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 58
A Research and Development team is creating a project plan for developing a new product. Upper management has requested the project be completed in 58 days. They have developed estimated time durations in days for the project as shown in the following table.
| Activity | Immediate Predecessor Activities | Optimistic Time (to) | Most Likely Time (tm) | Pessimistic Time (tp) |
|---|---|---|---|---|
| A | 9 | 11 | 14 | |
| B | A | 5 | 9 | 13 |
| C | A | 9 | 14 | 19 |
| D | A | 8 | 8 | 17 |
| E | B | 4 | 5 | 7 |
| F | C, E | 9 | 11 | 12 |
| G | B | 11 | 13 | 15 |
| H | B, D | 17 | 20 | 23 |
| I | B, D | 9 | 14 | 19 |
| J | F, G, H | 7 | 9 | 13 |
Determine the estimated duration of the project.
A) 50 days
B) 56 days
C) 71 days
D) 79 days