Question: A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs

A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different items at the same time.

Task

Task time per worker

Number of workers

1

2 minutes

1

2

6 minutes

1

3

14 minutes

2

4

4 minutes

1

5

15 minutes

3

  1. What is the capacity (hourly) of the process as a whole?
  2. What is the bottleneck of the process?
  3. What is the throughput time (assuming no wait time)?
  4. Where would you expect customers to wait?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!