Question: A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs
A service has five tasks, performed in sequence. In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different items at the same time.
| Task | Task time per worker | Number of workers |
| 1 | 2 minutes | 1 |
| 2 | 6 minutes | 1 |
| 3 | 14 minutes | 2 |
| 4 | 4 minutes | 1 |
| 5 | 15 minutes | 3 |
- What is the capacity (hourly) of the process as a whole?
- What is the bottleneck of the process?
- What is the throughput time (assuming no wait time)?
- Where would you expect customers to wait?