Question: A service has five tasks, performed in sequence.In the instance when there is more than one worker assigned to a task, each worker performs the
A service has five tasks, performed in sequence.In the instance when there is more than one worker assigned to a task, each worker performs the entire task and they both can be working on different "items" at the same time.
Task 1 2 3 4 5
Task time per worker 2 min 6 min 10 min 4 min 15 min
# of workers 1 1 1 1 2
- What is the capacity (hourly) of the process as a whole?
- What is the bottleneck of the process?
- What is the throughput time (assuming no wait time)?
- Where would you expect customers to wait?