Question: A shoe repair operation uses a two - step sequence that all jobs in a certain category follow. All jobs can be split in half

A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed:
\table[[,JOB TIMES (minutes)],[,A,B,C,D,E],[Workstation A,27,18,70,26,15],[Workstation B,45,33,30,24,10]]
Click here for the Excel Data File
a. Find the sequence that will minimize total completion time.
The sequence is
B-A-C-D-E
b. Determine the amount of idle time for workstation B.
minutes