Question: A shoe repair operation uses a two - step sequence that all jobs in a certain category follow. All jobs can be split in half

A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed:
\table[[,J0B TIMES (minutes)],[,A,B,C,D,E],[Workstation A,27,18,76,26,15],[Warkstation B,45,33,36,24,10]]
Click here for the Excel Data File
a. Find the sequence that will minimize total completion time.
The sequence is
b. Determine the amount of idle time for workstation B.
Idle time
minutes