Question: A shoe repair operation uses a two- step sequence that all jobs in a certain category follow. All jobs can be split in half at
A shoe repair operation uses a two- step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed,
.png)
a. Find the sequence that will minimize total completion time.
b. Determine the amount of idle time for workstation B.
c. What jobs are candidates for splitting? Why? If they were split, how much would idle time and makespan time bereduced?
Step by Step Solution
There are 3 Steps involved in it
a Find thesequence that will minimize total completion time Wewill use Johnsons rule to sequence the jobs The Johnsons rule steps from thetext are shown below 1 Select the job with the shortest time I... View full answer