Question: A shoe repair operation uses a two- step sequence that all jobs in a certain category follow. All jobs can be split in half at
A shoe repair operation uses a two- step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed,
.png)
a. Find the sequence that will minimize total completion time.
b. Determine the amount of idle time for workstation B.
c. What jobs are candidates for splitting? Why? If they were split, how much would idle time and makespan time bereduced?
JOB TIMES (minutes) 0 26 15 Workstation A 718 Workstation B 4 33 302410
Step by Step Solution
3.56 Rating (177 Votes )
There are 3 Steps involved in it
a Find the sequence that will minimize total completion time We will use Johnsons rule to sequence the jobs The Johnsons rule steps from the text are ... View full answer