Question: A simple CPM network has four activities, A, B, C and D as shown below. The latest start time (LS) for activity A is Activity
A simple CPM network has four activities, A, B, C and D as shown below. The latest start time (LS) for activity A is
| Activity | Duration | Immediate Predecessors |
| A | 18 | -- |
| B | 20 | -- |
| C | 6 | A,B |
| D | 5 | B |
| 20 | ||
| 0 | ||
| 2 | ||
| 1 | ||
| 18 |