Question: A simple CPM network has four activities, A, B, C and D as shown below. The latest start time (LS) for activity A is Activity

A simple CPM network has four activities, A, B, C and D as shown below. The latest start time (LS) for activity A is

Activity

Duration

Immediate

Predecessors

A

18

--

B

20

--

C

6

A,B

D

5

B

20

0

2

1

18